MANUFACTURING AND SUPPLY OF SCREW AXIS MAGAZINE CATCH TO D.S.CAT NO.5305 - 018183 D.C. NO. 25762-SA DT. 10-6-03. (REQUIRED IN WHITE FINISHED CONDITION) WITH FIRMS MATERIAL
Specification
AS PER D.S.CAT NO.5305 - 018183 D.C. NO. 25762-SA DT. 10-6-03. (REQUIRED IN WHITE FINISHED CONDITION) WITH FIRMS MATERIAL
MANUFACTURING AND SUPPLY OF PIN AXIS TRIGGER AND SEAR TO D.S. CAT NO. 5315 - 009113 D.C. NO. 25060-SA DT. 05-7-01 (WHITE FINISHED STAGE) WITH FIRMS MATERIAL (ICR - 1220)
Specification
AS PER D.S. CAT NO. 5315 - 009113 D.C. NO. 25060-SA DT. 05-7-01 (WHITE FINISHED STAGE) WITH FIRMS MATERIAL (ICR - 1220)
MFG. & SUPPLY OF PLUNGER LEVER CHANGE TO DS CAT NO. 1005-001647 DC NO. 19855-SA DT. 1/12/87 REQUIRED IN WHITE FINISHED CONDITION. (WITH FIRMS MATERIAL) ICR - 1315
Specification
AS PER DS CAT NO. 1005-001647 DC NO. 19855-SA DT. 1/12/87 REQUIRED IN WHITE FINISHED CONDITION. (WITH FIRMS MATERIAL) ICR - 1315
PIN,EJECTOR LOWER TO DS CAT NO. 5315-001757 DC NO.25142-SA DT.10/10/01 FOR DC NO. LATEST ISSUE TO BE FOLLOWED (WHITE FINISHED CONDITION WITH FIRM MATERIAL) (ICR-1327)
Specification
AS PER DS CAT NO. 5315-001757 DC NO.25142-SA DT.10/10/01 FOR DC NO. LATEST ISSUE TO BE FOLLOWED (WHITE FINISHED CONDITION WITH FIRM MATERIAL) (ICR-1327)
Drawing no.
DS CAT NO. 5315-001757 DC NO.25142-SA DT.10/10/01 (ICR-1327)
PIN EJECTOR UPPER TO DS.CAT.NO. 5315-001758 DC NO.25999-SA DT.20-10-04 FOR DC NO. LATEST ISSUE TO BE FOLLOWE (WHITE FINISHED CONDITION WITH FIRM MATERIAL) (ICR-1326)
Specification
AS PER DS.CAT.NO. 5315-001758 DC NO.25999-SA DT.20-10-04 FOR DC NO. LATEST ISSUE TO BE FOLLOWE (WHITE FINISHED CONDITION WITH FIRM MATERIAL) (ICR-1326)
Drawing no.
DS.CAT.NO. 5315-001758 DC NO.25999-SA DT.20-10-04 (ICR-1326)
SUPPLY OF BLOCK EJECTOR ICR-1324 TO DS.CAT.N0:1005-001513 DC.NO.26758-SA DATED 28.05.15 FULLY FINISHED CONDITION WITH FIRM MATERIAL. LATEST ISSUE TO BE FOLLOWED.
Specification
AS PER ICR-1324 TO DS.CAT.N0:1005-001513 DC.NO.26758-SA DATED 28.05.15 FULLY FINISHED CONDITION WITH FIRM MATERIAL. LATEST ISSUE TO BE FOLLOWED.
Drawing no.
ICR-1324 TO DS.CAT.N0:1005-001513 DC.NO.26758-SA DATED 28.05.15
ST.FLAT 125 X 8 X 530 MM LONG IN CUT LENGTH IN H.R & NORM. CONDN. TO SPECN.IS:5517-1993 DESIGNATION 55C8 TEST PIECE TO BE TESTED AS PER SPECN.TOLLERANCE ON WIDTH +/-2MM,ON THICKNE
SS +/-0.25MM.
Specification
ST.FLAT 125 X 8 X 530 MM LONG IN CUT LENGTH IN H.R & NORM. CONDN. TO SPECN.IS:5517-1993 DESIGNATION 55C8 TEST PIECE TO BE TESTED AS PER SPECN.TOLLERANCE ON WIDTH +/-2MM,ON THICKNE
SS +/-0.25MM.
1. Cold drawing process line of adequate capacity to manufacture cold deformed hexagonal bar.
2. Suitable end finishing machine for carrying out cutting of cold deformed hexagonal bar to required length by cold machining.
3. Turning / thread rolling / thread forming machine.
Hot Rolling.
Isothermal heat treatment line to achieve required mechanical properties as specified.
Shot Blasting
Facility of Zinc coating and Chromate passivation.
Facility for removal of Hydrogen Embrittlement.
Crack detection testing facility.
Bend removing (straightening) machine.
Bend test facility.
Mechanical, metallurgical and Chemical analysis testing facilities to test the required parameters as specified in specification no.OFM/TDS/TRACK-72/02.
NUT TO DRG.NO.613.44.071,TECHNICAL REQUIREMENT AS PER SPEC. NO.OFM/TDS/TRACK-72/O3
Drawing no.
DRG.NO.613.44.071
Manufacturing Technology
1. Cold drawing process line of adequate capacity to manufacture cold deformed hexagonal bar.2. Suitable end finishing machine for sizing of cold deformed hexagonal bar to required length by cold machining.
Hot Rolling. Suitable heat treatment line to achieve required mechanical properties as specified.
Facility of Zinc coating and Chromate passivation.
Testing / Inspection Facility
Crack detection testing facility.
Mechanical, metallurgical and Chemical analysis testing facilities to test the required parameters as specified in specification no.OFM/TDS/TRACK-72/03.
RUBBERISING OF SHORT BUSHING TO DRg.No.613.44.061, AS PER SPEC.No.OFM/TDS/TRACK-72/04 AND COMPLETE ASSEMBLY DRg.No.613.44.057 Cb.
Drawing no.
DRg.No.613.44.061,
Manufacturing Technology
1. Injection moulding machine.
Testing / Inspection Facility
1. Tensile strength testing facility.
2. Hardness testing facility.
3. Brittleness testing facility at low temperature.
4. Bonding strength test facility.
5. Service life (Endurance) test facilities.
6. Testing facilities as per specification no. OFM/TDS/TRACK-72/04.
1. Tensile strength testing facility.
2. Hardness testing facility.
3. Brittleness testing facility at low temperature.
4. Bonding strength test facility.
5. Service life (Endurance) test facilities.
6. Testing facilities as per specification no. OFM/TDS/TRACK-72/04.
RUBBERISING OF LONG BUSHING TO DRg.No.613.44.059,AS PER SPEC.No.OFM/TDS/TRACK-72/04 AND COMPLETE ASSEMBLY DRg.No.613.44.055 Cb.
Drawing no.
DRg.No.613.44.059
Manufacturing Technology
1. Injection moulding machine.
Testing / Inspection Facility
1. Tensile strength testing facility.
2. Hardness testing facility.
3. Brittleness testing facility at low temperature.
4. Bonding strength test facility.
5. Service life (Endurance) test facilities.
6. Testing facilities as per specification no. OFM/TDS/TRACK-72/04.
SHORT BUSHING TO DRG. NO.613.44.061, TECHNICAL REQUIREMENTS AS PER SPEC. NO. OFM/TDS/TRACK-72/01.
Drawing no.
Manufacturing Technology
DRG. NO.613.44.061
1. Cold drawing process line of adequate capacity to manufacture cold deformed pipe with inner hexagonal profile.2. Heat treatment line to achieve required mechanical properties as specified.3. Suitable end finishing machine for carrying out cutting of cold deformed pipe with inner hexagonal profile to required length by cold machining.
Hot Rolling.
Testing / Inspection Facility
Mechanical, metallurgical, chemical analysis and crack detection testing facilities to test the required parameters as specified in specification no. OFM/TDS/TRACK-72/01.
MEDIUM BUSHING TO DRG. NO.613.44.060, TECHNICAL REQUIREMENTS AS PER SPEC. NO. OFM/TDS/TRACK-72/01.
Drawing no.
DRG. NO.613.44.060
Manufacturing Technology
1. Cold drawing process line of adequate capacity to manufacture cold deformed pipe with inner hexagonal profile.2. Heat treatment line to achieve required mechanical properties as specified. 3. Suitable end finishing machine for carrying out cutting of cold deformed pipe with inner hexagonal profile to required length by cold machining.
Hot Rolling.
Testing / Inspection Facility
Mechanical, metallurgical, chemical analysis and crack detection testing facilities to test the required parameters as specified in specification no. OFM/TDS/TRACK-72/01.
1. Cold drawing process line of adequate capacity to manufacture cold deformed pipe with inner hexagonal profile. 2. Heat treatment line to achieve required mechanical properties as specified. 3. Suitable end finishing machine for carrying out cutting of cold deformed pipe with inner hexagonal profile to required length by cold machining
Mechanical, metallurgical, chemical analysis and crack detection testing facilities to test the required parameters as specified in specification no. OFM/TDS/TRACK-72/01.