आयुध निर्माणी परियोजना कोरवा
Ordnance Factory Project Korwa
Home
About
Factory
Timeline
Mission & Vision
Quality Control Setup
Quality Policy
Testing Facilities
Weapon Testing Facilities
Special Purpose Testing Instruments
Our Products
TAR 7.62 x 39 mm
PAG 12 Bore
RTI
RTI Officers
RTI Act
Events
Rajbhasha
Quarterly News
Rajbhasha Vibhag
Avadhvaani annual magzine
IB GUEST HOUSE BOOKING
More
Downloads
Contact Us
Timeline
Home
/
Timeline
2
nd
Dec’ 2007 :OFPKR was set up by
Ministry of Defence.
27
th
Apr’ 2009 :The first production shop (
Assembly
) inaugurated.
1
st
Oct’ 2011 :Project Office shifted from Lucknow to
Korwa.
26
th
Aug’ 2013 :First product (PAG) issued to Chhattisgarh Police.
28
th
June’ 2016 :Lease deed for land signed with HAL
Korwa
.
19
th
Oct’ 2016 :Land acquisition for residential estates signed
with State Government.
21
st
May’ 2017 :Possession of 39.02 acres land of
Rajapur
Kalyan
Village
taken over.
06
th
Jan ’ 2018 :Contract for Civil Work of residential estate awarded by DRDO.
02
nd
Aug ’ 2019 : Possession of 14.56 acres land of
Kudwa
Village
for Factory extension taken over.